Renewables Success Story

Full EPC, 70 MWp project for Eurowind Teius.

With an installed capacity of 68.99 MW the Teius park is equipped with tracking systems that follow the sun throughout the day, ensuring maximum energy efficiency. With an annual output of over 103 GWh, CEF Teius will generate enough clean energy to power more than 25,000 households.

ENEVO Group led the project’s EPC execution. The scope included design, procurement, installation, and commissioning of the PV plant, a 110/20kV substation, and an 80 MVA transformer station—built to the highest standards of quality and in full compliance with Romanian grid connection regulations.