Power T&D Main References
110/20kV Substation – SATU MARE 2 – CEF Botiz, 27MWp
ENEVO Group implemented a turnkey project for the 27 MWp photovoltaic plant Satu Mare 2 – CEF Botiz, delivering the complete construction of the 110/20kV electrical substation and the 20kV underground line connecting it to the PV plant.
The substation includes an 110kV bay, a 110/20kV 31.5 MVA power transformer, multiple 20kV bays, network neutral treatment, auxiliary services, and reactive power compensation with a capacitor bank. ENEVO carried out the full in-house design for the civil works, primary equipment, protection, and SCADA systems.



Automation Main References